The energy market in general, and the wind energy market in particular, are experiencing constant decrease of prices, together with harsher and harsher grid conditions. In order to comply with worldwide environmental policies, revolutionary solutions, such as FASTAP, need to reach the market as soon as possible.
The FASTAP project aims at scaling from TRL6 to TRL8 the wind turbine application of a very fast on-load tap changer transformer technology. This solution uses thyristors specially connected to multi-tap transformer windings to provide On-Load Tap Changer capability to a standard wind turbine (WTG) transformer. This technology allows to choose the optimum voltage at which the WTG operates in, not only in steady-state conditions but also for dynamic and transient events.
This technology will increase WTGs' electric capabilities in weak grid conditions, enlarge WTGs' Low and High Voltage Ride Through capabilities and allow reducing electrical components oversizing. As an overall, the FASTAP will be able to reduce wind's Leverage Cost of Energy up to 5.5% and will be able to connect to worldwide grids an additional 71.64GW wind capacity.
The consortium partners have been working together for the last three years to bring the technology up to TRL6. They cover the whole value chain, which guarantees that the product will reach the market 33 months after the project kicks-off:
FASTAP
CLOSED
EIC-FTI-2018-2020
3.941.214,76 €
2.996.935,00 €
SIEMENS GAMESA RENEWABLE ENERGY AS
BRANDE, DK
SIEMENS GAMESA RENEWABLE ENERJI ANONIM SIRKETI
Istanbul, TR
STARKSTROM-GERATEBAU GESELLSCHAFT MIT BESCHRANKTER HAFTUNG
Regensburg, DE
SACHSISCH-BAYERISCHE STARKSTROM-GERATEBAU GMBH
Neumark, DE
INFINEON TECHNOLOGIES BIPOLAR GMBH& CO. KG
Warstein, DE
SIEMENS GAMESA RENEWABLE ENERGY INNOVATION & TECHNOLOGY S.L.
SARRIGUREN, ES
MONDRAGON GOI ESKOLA POLITEKNIKOA JOSE MARIA ARIZMENDIARRIETA S COOP
ARRASATE, ES